Construction is now underway for Fairmont's 6.5
million dollar sewer lines improvement project. "We want
everyone to know that they will see ongoing work being done in
several areas around town." say Project Coordinator Steve Cain of
Greenhorne & O'Mara Enterprises. "Residents can expect to see
orange cones and blocked avenues while construction continues in and
around the area." Most of the construction is slated for
completion around July of this year.
To finance the project, Fairmont is utilizing a 1
million dollar federal grant funds and finance the remainder.
The Public Service Commission approved a rate hike to assist in
paying for the project back in 2006. "As the projects are
completed, we feel that many of issues within the sanitary sewer
will go away," says David Sago, Utility Manager. "We are
putting a great deal of focus on these projects. We are
utilizing all available manpower and consultation of engineering
firms to see that our efforts are seen through to their completion.
Project to Address Watson area
Flooding
A project is underway to eliminate much of flooding
that occasionally occurs in Fairmont. Over the past 20 years,
a plan to eliminate flooding in the Watson area has been on the
utility books. But it took the creation of Stormwater
Department to finally see the project through. Watson flooding
is on the radar screen and is currently being addressed by
construction crews. A new 30' line is being installed to
replace the existing 20' line that was found to be inadequate for
storm water removal in the area.
Mike DeMary, Program Manager states, "Watson is not
the only area affected by flooding due to heavy rain events, but we
are prioritizing the projects so when the funding becomes available
we'll have a rational method of where we're going, a method of
selecting." If you would like to know more about the ongoing
storm water projects feel free to contact Mike DeMary at: (304)
366-0540 or email: mdemary@fairmontwv.gov